A Request for Further Information (RFI) was received from An Bord Pleanála in relation to the planning application for the proposed Lyrenacarriga Wind Farm. All documentation related to this RFI has now been submitted to An Bord Pleanála. The full planning application and subsequent additional information related to the RFI is available for review at:
lyrenacarrigawindfarm.comNovember 2022 Update


In light of the Covid-19 restrictions, we are pleased to share our virtual public exhibition with you. If you click on this link, you will be able to view updated project information, photomontages and the proposed turbine layout: https://www.innovision.ie/lyrenacarriga
If you would like more information or would like to discuss your comments:
– Email: lyre@rwe.com
– Telephone: 056 771 5782 during office hours. (9.00am – 5.00pm Monday to Friday)
– Look at the comprehensive set of Frequently Asked Questions (FAQs) available to download from this webpage
Proposed Turbine Layout

Useful documents


Frequently asked questions
Please find below responses to the most common questions raised during one-to-one consultations within the local community. A comprehensive response to all the questions asked is also available for viewing or download above.
Health
What impact will the wind farm have on health of all neighbours (including animals)?
A detailed and systematic assessment of the potential impacts on Population and Human Health as a result of the proposal has been undertaken as part of the Environmental Impact Assessment (EIAR) for the proposed Development at Lyrenacarriga. The findings of this assessment and details of related measures proposed in order to protect the surrounding environment from any potentially negative effects on Human Health will be available for review within the EIAR which will be submitted as part of the Planning Application.
There is no empirical evidence to suggest that the existence of a wind farm has an impact on human health (Common Concerns about Wind Power - 2nd ed Centre for sustainable Energy, June 2017). RWE has designed a windfarm that optimizes location of turbines so that they both capture the maximum energy possible whilst also following best practice guidelines. See also responses to FAQs on Shadow flicker, Noise and Ecology.
Shadow Flicker
What is shadow flicker? How does this impact on health?
Shadow flicker is the name given to a phenomenon caused when the sun is behind the turbine blades as it rises or sets, casting a moving shadow over a small opening in a building such as a window, creating a flickering effect within the building.
The ‘Wind Energy Development Guidelines for Planning Authorities’ (Department of the Environment, Heritage and Local Government, 2006) set out limits for the control of shadow flicker from wind energy developments to prevent any nuisance and to prevent any impacts on health. Current guidance limits allow shadow flicker to 30 minutes per day for a maximum of 30 hours per year. The Lyre Wind Farm has been designed to utilise advancements in turbine technology to ensure that the effect of shadow flicker is eliminated and will not affect any inhabited properties.
The Department of Housing, Planning and Local Government (DHPLG) published “Draft Revised Wind Energy Development Guidelines” in December 2019 and these draft guidelines were under public consultation until 19th February 2020. The draft guidelines take account of a previous “Targeted Review” consultation undertaken in by the DHPLG 2013 and subsequent detailed engagement between the relevant Government Departments culminating in a “Preferred Draft Approach” , which was announced in June 2017 to inform and advance the conclusion of the review.
The design of the proposed development at Lyrenacarriga has taken account of the 2017 “Preferred Draft Approach” and has also taken account of the provisions of the 2019 “Draft Revised Wind Energy Development Guidelines”. At time of writing, the 2019 Draft Revised Wind Energy Development Guidelines are not yet in force may be subject to further change on foot of completion of the public consultation process, so the relevant guidelines remain those published in 2006.
Should the revised Wind Energy Development Guidelines be finalised in advance of a planning decision being made on the proposed development, with current shadow flicker thresholds being amended, if necessary, the proposed development can comply with any revised shadow flicker requirements by implementing mitigation by design (as detailed in the EIAR) through turbine selection and use of the flexible built-in turbine control systems.
Noise
What level of noise will come from these turbines?
The ‘Wind Energy Development Guidelines for Planning Authorities’ (Department of the Environment, Heritage and Local Government, 2006) set out strict limits for the control of noise from wind energy developments to prevent undue noise pollution and to prevent any impacts on health.
The Department of Housing, Planning and Local Government (DHPLG) published “Draft Revised Wind Energy Development Guidelines” in December 2019 and these draft guidelines were under public consultation until 19th February 2020. The draft guidelines take account of a previous “Targeted Review” consultation undertaken in by the DHPLG 2013 and subsequent detailed engagement between the relevant Government Departments culminating in a “Preferred Draft Approach” , which was announced in June 2017 to inform and advance the conclusion of the review.
The design of the proposed development at Lyrenacarriga has taken account of the 2017 “Preferred Draft Approach” and has also taken account of the provisions of the 2019 “Draft Revised Wind Energy Development Guidelines”. At time of writing, the 2019 Draft Revised Wind Energy Development Guidelines are not yet in force may be subject to further change on foot of completion of the public consultation process, so the relevant guidelines remain those published in 2006.
Should the revised Wind Energy Development Guidelines be finalised in advance of a planning decision being made on the proposed development, with current noise thresholds being amended, if necessary, the proposed development can comply with any revised noise requirements by implementing mitigation by design (as detailed in the EIAR) through turbine selection and use of the flexible built-in turbine control systems.
Infrasound
What will the level of the infrasound be coming from these turbines? What impact will this have on health of all neighbours?
Infrasound is a common term given to a specific range of low-frequency noise normally considered inaudible to the human ear. Low Frequency Noise is noise that is dominated by frequency components less than approximately 200Hz, whereas infrasound is typically described as sound at frequencies below 20Hz. As noted in the Environmental Protection Agency document ‘Guidance Note for Noise Assessment of Wind Turbine Operations at EPA Licensed Sites (NG3)’ (2011), there is no empirical evidence that infrasound emanating from a wind farm causes ill health.
A German report entitled “Low Frequency Noise incl. Infrasound from Wind Turbines and Other Sources” presents the details of a measurement project which ran from 2013. The report was published by the State Office for the Environment, Measurement and Nature Conservation of the Federal State of Baden-Württemberg in 2016 and concluded the following in relation to infrasound from wind turbines:
“The measured infrasound levels (G levels) at a distance of approx. 150 m from the turbine were between 55 and 80 dB(G) with the turbine running. With the turbine switched off, they were between 50 and 75 dB(G). At distances of 650 to 700 m, the G levels were between 55 and 75 dB(G) with the turbine switched on as well as off.”
“For the measurements carried out even at close range, the infrasound levels in the vicinity of wind turbines – at distances between 150 and 300 m – were well below the threshold of what humans can perceive in accordance with DIN 45680 (2013 Draft)”
“The results of this measurement project comply with the results of similar investigations on a national and international level.”
Layout
When will we see the final turbine layout?
Why has the number reduced from 25 to 17 turbines?
Is the 700m set back distance measured from the main dwelling or the boundary of the property?
Aviation & Atmospheric Interference
What will the effects of the red lights on top of the turbines during the night be?
What are the impacts on climate and air quality?
Will the turbines affect drone activity & recreation?
Ecology
What are the impacts on flora and fauna?
A detailed and systematic assessment of potential impacts on Ecology as a result of the proposal has been undertaken as part of the Environmental Impact Assessment (EIA) for the proposed Development at Lyrenacarriga . The potential effects of the proposed development on avifauna, terrestrial and aquatic and flora and fauna during the construction, operation and decommissioning phases have been assessed. The findings of this assessment and details of mitigation measures proposed in order to protect the surrounding environment from any potentially negative impacts on Ecology will be available for public within the EIAR which will be submitted as part of the Planning Application.
Under the European Habitats Directive, the proposed development is subject to the Article 6(3) Appropriate Assessment (AA) Process. An AA Screening and a Natura Impact Statement, have been prepared in accordance with the European Commission guidance document Assessment of Plans and Projects Significantly affecting Natura 2000 Sites: Methodological Guidance on the provisions of Article 6(3) and 6(4) of the Habitats Directive 92/43/EEC (EC, 2001) and the Department of the Environment’s Guidance on the Appropriate Assessment of Plans and Projects in Ireland (December 2009, amended February 2010).
What effect will this development have on local equine enterprise and agriculture enterprise?
When will the EIAR be available?
The EIAR will accompany the planning application and will be available to the public to read from the start of the public consultation process, which begins after the planning application is submitted. The information gathered during our community consultation will also be fed directly back into the EIAR to further inform the final design of the windfarm. These surveys are nearly completed and include the topics listed below:
Population & Human Health |
Hydrology & Hydrogeology |
Biodiversity Birds |
Shadow Flicker |
Air and Climate |
Landscape & Visual |
Biodiversity Flora & Fauna |
Noise and Vibration |
Lands, Soils & Geology |
Archaeological, Architecture & Cultural Heritage |
Material Assets |
|
Drinking Water & Aquatic Ecology Impacts
What will be the impacts on water and sources of our water supply?
As part of the EIA process, a hydrological and hydrogeological consultant has carried out a comprehensive investigation and evaluation of the surface and ground water systems specific to the site and surrounding catchments. Irish Water have additionally been engaged to ascertain any necessary additional information in relation to the water treatment facilities at both Youghal and Tallow.
Information pertaining to these treatment plants, the feed-in sources and associated facilities have been inspected and traced. From this, mitigation strategies have been formulated to protect water quality. In general, irrespective of the direction of groundwater flow, the hydrological assessment for the EIAR assumes that all properties located around the Lyre site have a groundwater well and the appropriate measures against any potential effects on these or any water supply have been proposed to be employed on this basis.
What are the impacts if peat bog areas get “sealed” to provide foundation for the turbines?
Are there provisions to prevent water getting heavily silted?
What are the impacts to aquatic life?
Traffic Management Plan, Local Infrastructure & Services Provider
What will be the impacts on local infrastructure and use of local roads?
What are the impacts on mobile phone / mobile broadband / TV reception?
Scoping and consultation with national and regional broadcasters has been undertaken as part of the EIA process. This consultation together with a robust assessment completed as part of the EIA has confirmed that the current layout has no turbines within areas requested to be left clear by consulted telecoms utilities and broadcasters. Subject to planning approval and prior to the commencement of construction, a follow up pre-construction telecommunications survey would be conducted to assess communication infrastructure in further detail , including reception and coverage locally. This will ensure that any necessary mitigation measures as identified and proposed in the EIAR as part of the assessment are in put in place to avoid any potentially negative impacts on telecommunications.
The ‘Wind Energy Development Guidelines for Planning Authorities’ (Department of the Environment, Heritage and Local Government, 2006) states that interference with broadcast communications can be overcome for example by the installation of deflectors or repeaters mounted on mitigation masts if required.
Tourism
What will the impacts on tourism be?
There is no evidence that wind farms negatively affect tourism. With regard to recreation and tourism assets in the area, no direct or indirect negative effects are expected during the construction or operation of the proposed development.
BiGGAR Economics undertook an independent study in Scotland in 2016, entitled ‘Wind Farms and Tourism Trends in Scotland’. Overall, the study stated that there is no negative relationship between the development of onshore wind farms and tourism employment within the Scottish economy, at local authority level, or areas immediately surrounding wind farm development.
A Fáilte Ireland survey found that of 1,000 domestic and foreign tourists who holidayed in Ireland during 2012, over half of tourists said that they had seen a wind turbine while travelling around the country. Of this number of tourists, 21% claimed wind turbines had a negative impact on the landscape. However, 32% said that it enhanced the surrounding landscape, while 47% said that it made no difference to the landscape. Almost 75% of respondents claim that potentially greater numbers of wind farms would either have no impact on their likelihood to visit or have a strong or fairly strong positive impact on future visits to the island of Ireland. (Fáilte Ireland Newsletter 2012/No.1 ‘Visitor Attitudes on the Environment: Wind Farms – Update on 2007 Research’).
Carbon footprint of turbine manufacture & construction
The EIAR for the proposed development includes a detailed analysis of the Carbon Dioxide (CO2) losses and savings associated with the proposed development. The model used for calculating CO2 losses is based on the ‘Calculating carbon savings from wind farms on Scottish peat lands’ methodology, established in 2008 (and updated in 2011) by scientists at the University of Aberdeen and the Macaulay Institute, with support from the Rural and Environment Research and Analysis Directorate of the Scottish Government, Science Policy and Co-ordination Division. While there is no peat present at the proposed development site, the Macaulay Institute model can be used to calculate all potential CO2 expected to be generated by proposed wind farm, associated with the manufacture, transportation and erection of turbines, including felling of forestry and the removal of vegetation.
The CO2 offset, or savings, associated to the proposed wind farm has also been calculated, based on the rated capacity of the proposal (in MW) , the capacity or load factor which takes into account the intermittent nature of the wind, the availability of wind turbines and array losses etc., the carbon load in grams per kWh (kilowatt hour) of electricity generated and distributed via the national grid. The carbon load figure is provided annually by the Sustainable Energy Authority of Ireland. This calculation shows how many tonnes of CO2 will be displaced / saved per annum as a result of operation of the proposed wind farm.
Overall, for the majority of wind farms, the amount of CO2 that is lost to the atmosphere as a result of their construction and operation is offset by the CO2 savings made by the wind farm within approximately its first year of operation.
Cumulative Effect on the Neighbourhood & Property
What cumulative impact will this procet have on the value of the neighbourhood?
Evidence from operational wind farms indicates that a well-designed and implemented project, in conjunction with the community benefit fund and local business rates contribution, has indirect positive effect on the local area. Making use of new and existing tracks as sport and leisure facilities (e.g. in the form of nature trails, walking routes, cycle tracks, outdoor gyms and equine trails) can be a welcome addition to the local community see https://www.scottishpower.co.uk/whitelee/ and https://www.bordnamona.ie/corporate-responsibility/amenities/mount-lucas/
Under new industry guidelines, community benefit funding underpins project proposals and approval. RWE envisage the implementation of a community benefit fund that would be set up and designed to enable the community themselves to manage and implement funding for clubs or groups, local projects, develop facility’s and amenities that they would like to see.
What impact will the project have on the property prices?
Community Consultation
Can you clarify which individuals and/or groups have been consulted within the community?
- A public information day was held 31st May 2018 in KGK Community Centre in Knockanore from 4pm – 9pm.
- A door – to – door engagement programme ran from August to October 2018, where every house within 2km of the proposed project was approached. In the event of no one being home, contact details were left to facilitate a call back.
- Members of the community continue to be invited to get in touch with queries or concerns about the project by calling 056 771-5782 or emailing lyre@rwe.com. The project team will be available to discuss the final layout and results of the EIA. Also we will have useful hyperlinks to references and studies mentioned in this document on the website.
- A letter was delivered to all houses within 2km of the proposed project in November 2018. It listed the queries and concerns locally up to that point. A Frequently Asked Questions section was added to the project website in March 2019 on the basis of feedback and follow up queries received in relation to the proposal and the information provided to date.
We would like to hear from you about this proposed project. Please contact us on 056-771-5782 or at lyre@rwe.com to organise a private one to one consultation with a member of the innogy project team to discuss any points mentioned in this letter or renewable energy in general and how it can benefit your community.